Question on: JAMB Accounting - 2021


The prime cost is the total of the

A
direct materials+direct labour+direct wages
B
production cost+selling expenses
C
administrative expenses+selling expenses+distribution expenses
D
direct materials+work overhead expenses
Ask EduPadi AI for a detailed answer
Correct Option: A